Which document contains the start date and duration/performance period of the contract?

The key idea is that official contract timing is set by the authorization to start work. The document that provides the exact start date and the duration or performance period is the Notice to Proceed. It formally grants the contractor permission to begin and defines how long the work should take, which is essential for scheduling, milestones, and payments. Other documents serve different purposes. A form like Air Force Form 103 is mainly an administrative/financial instrument, not the start signal for performance. A Construction Permit authorizes work from a regulatory standpoint but does not establish the contract’s start date or its overall duration. Build Authority isn’t a standard instrument for initiating contract performance with timing.

The key idea is that official contract timing is set by the authorization to start work. The document that provides the exact start date and the duration or performance period is the Notice to Proceed. It formally grants the contractor permission to begin and defines how long the work should take, which is essential for scheduling, milestones, and payments.

Other documents serve different purposes. A form like Air Force Form 103 is mainly an administrative/financial instrument, not the start signal for performance. A Construction Permit authorizes work from a regulatory standpoint but does not establish the contract’s start date or its overall duration. Build Authority isn’t a standard instrument for initiating contract performance with timing.